Satu sesi pembelajaran dan bimbingan teknikal berkaitan kaedah pemasangan IBS V-Plus Panel telah berjaya dilaksanakan di Tok Bali, Pasir Puteh, Kelantan. Program ini dianjurkan bagi meningkatkan kefahaman dan kemahiran para tukang dalam pemasangan sistem binaan berindustri (IBS) secara lebih sistematik, selamat dan berkualiti. Dalam usaha memastikan kaedah pemasangan dipatuhi mengikut spesifikasi teknikal yang ditetapkan, pihak AZ Mega Plus Group Sdn. Bhd. telah menghantar staf projek ke lokasi bagi memberikan tunjuk ajar secara langsung kepada semua peserta yang terlibat.

Sepanjang sesi berlangsung, staf projek telah memberi penerangan terperinci berkenaan teknik locking panel yang betul menggunakan besi R6 dan Y10. Bagi memastikan kekuatan struktur panel berada pada tahap optimum, locking pada bahagian atas dan bawah panel menggunakan besi Y10 sebagai elemen utama pengukuhan. Selain itu, sambungan antara panel di bahagian atas, tengah dan bawah pula dipasang menggunakan besi R6 yang dibentuk seperti stapler untuk mengukuhkan sambungan panel serta memastikan kedudukan panel lebih stabil semasa proses pemasangan dijalankan.

Seterusnya, para peserta turut didedahkan dengan kaedah tambahan bagi meningkatkan ketahanan sambungan panel iaitu penggunaan steel mesh yang ditampal pada bahagian sambungan selepas pemasangan besi locking selesai dilakukan. Kaedah ini penting bagi mengurangkan risiko keretakan pada sambungan serta membantu menghasilkan kemasan akhir yang lebih kukuh dan kemas. Penerangan secara teori dan praktikal ini memberi peluang kepada para tukang untuk memahami setiap langkah kerja dengan lebih jelas sebelum diaplikasikan di tapak projek sebenar.

Melalui sesi bimbingan ini, para tukang bukan sahaja dapat memahami teknik pemasangan IBS V-Plus Panel dengan lebih tepat, malah turut didedahkan kepada kepentingan pematuhan kaedah kerja standard bagi mengelakkan kesilapan pemasangan yang boleh menjejaskan kekuatan struktur bangunan. Pendekatan latihan secara praktikal di tapak memberi peluang kepada peserta untuk terus mempraktikkan teknik locking panel, pemasangan steel mesh serta kaedah penyambungan panel dengan pemantauan staf projek. Program seperti ini dilihat mampu meningkatkan tahap kemahiran tenaga kerja tempatan di samping memastikan setiap pemasangan dilaksanakan mengikut spesifikasi teknikal yang telah ditetapkan oleh pihak syarikat.

LEARNING SESSION AND GUIDANCE ON IBS V-PLUS PANEL INSTALLATION METHOD AT TOK BALI, PASIR PUTEH, KELANTAN

A learning and technical guidance session on the installation method of IBS V-Plus Panel was successfully conducted at Tok Bali, Pasir Puteh, Kelantan. This program was organized to enhance the knowledge and skills of workers in implementing the Industrialized Building System (IBS) installation in a more systematic, safe, and quality-oriented manner. To ensure that the installation method complies with the required technical specifications, AZ Mega Plus Group Sdn. Bhd. deployed project staff to the site to provide direct technical guidance and supervision to all participating workers.

Throughout the session, the project staff delivered a detailed explanation regarding the correct panel locking technique using R6 and Y10 steel bars. To ensure optimal structural strength, the upper and lower sections of the panel were locked using Y10 steel bars as the main reinforcement element. In addition, panel connections at the upper, middle, and lower sections were secured using R6 steel bars shaped like staples to strengthen the panel joints and maintain panel stability throughout the installation process.

Furthermore, participants were also introduced to an additional method to improve joint durability through the application of steel mesh at the connection areas after the locking installation was completed. This method is essential in minimizing the risk of cracks at panel joints while also contributing to a stronger and neater finishing result. The combination of theoretical explanation and practical demonstration provided workers with a clearer understanding of each installation step before applying the technique on actual project sites.

Through this guidance session, workers were not only able to gain a better understanding of the proper IBS V-Plus Panel installation techniques, but were also exposed to the importance of adhering to standard working procedures in order to avoid installation errors that may affect the structural integrity of the building. This hands-on training approach allowed participants to directly practice panel locking, steel mesh installation, and panel jointing techniques under the supervision of project staff. Programs such as this are seen as highly beneficial in improving the competency of local skilled workers while ensuring that all installations are carried out according to the technical specifications set by the company.