CARA PEMASANGAN LINTEL BEAM DI TAPAK PROJEK MENGGUNAKAN SISTEM IBS V-PLUS

CARA PEMASANGAN LINTEL BEAM DI TAPAK PROJEK MENGGUNAKAN SISTEM IBS V-PLUS

Pemasangan lintel beam merupakan salah satu kerja penting dalam pembinaan dinding menggunakan sistem IBS V-PLUS, terutamanya pada bahagian atas bukaan pintu dan tingkap. Lintel beam berfungsi untuk menampung beban dinding di atas bukaan tersebut dan memindahkan beban ke struktur sisi seperti panel atau tiang. Oleh itu, pemasangan yang betul amat penting bagi memastikan kestabilan dan keselamatan struktur bangunan.

Langkah pemasangan bermula selepas IBS V-PLUS Panel atau Big Block dipasang sehingga paras atas bukaan. Kedudukan lintel beam akan ditanda mengikut pelan pembinaan bagi memastikan panjang dan arasnya tepat. Sokongan sementara biasanya disediakan di bahagian bawah lintel beam untuk memastikan ia berada dalam keadaan rata dan stabil sebelum kerja penguncian dilakukan.

Seterusnya, lintel beam diletakkan di atas panel dengan kemas dan sejajar. Sambungan antara lintel beam dan sistem IBS V-PLUS akan diperkukuhkan menggunakan tetulang besi dan diisi dengan konkrit atau simen yang sesuai mengikut spesifikasi projek. Proses ini memastikan lintel beam terikat kukuh dengan struktur dinding dan mampu menampung beban dengan selamat.

Secara keseluruhan, pemasangan lintel beam menggunakan sistem IBS V-PLUS adalah lebih tersusun dan mudah dikawal dari segi kualiti. Dengan langkah kerja yang jelas dan penggunaan komponen IBS yang seragam, proses ini membantu mempercepatkan pembinaan di tapak projek serta memastikan hasil binaan yang kukuh, kemas dan menepati keperluan teknikal pembinaan moden.

INSTALLATION METHOD OF LINTEL BEAM ON SITE USING THE IBS V-PLUS SYSTEM

The installation of a lintel beam is an important construction process when using the IBS V-PLUS system, especially above door and window openings. The lintel beam functions to support the load of the wall above the opening and transfer it safely to the side structures such as panels or columns. Therefore, correct installation is essential to ensure the stability and safety of the building structure.

The installation process begins after the IBS V-PLUS Panel or Big Block has been installed up to the top level of the opening. The lintel beam position is marked according to the construction drawings to ensure accurate length and level. Temporary support is usually provided beneath the lintel beam to keep it level and stable before the locking or fixing works are carried out.

Next, the lintel beam is carefully placed on top of the panels and aligned properly. The connection between the lintel beam and the IBS V-PLUS system is strengthened using steel reinforcement and filled with suitable concrete or cement as specified in the project requirements. This process ensures that the lintel beam is firmly bonded to the wall structure and capable of carrying the imposed loads safely.

Overall, the installation of lintel beams using the IBS V-PLUS system is more systematic and easier to control in terms of quality. With clear installation steps and standardized IBS components, this method helps speed up on-site construction while ensuring a strong, neat, and technically compliant building outcome.